When the Problem Does Not Originate at the Production Line
A failure in an import transaction – whether a delay, a defect, or incomplete documentation – can easily lead to questioning the supplier's competence. Yet a distortion can arise at multiple points in the procurement chain and ultimately "land" at the manufacturer's doorstep.
International procurement is a complex system: technical specification, price quotation, Incoterms terms, payment structure, quality control, logistics organisation. If any of these points is imprecise, the error often originates not with the manufacturer but on the buyer's side.
Imprecise Specifications and Communication
One of the most common sources of internally generated import errors is an insufficiently detailed technical or commercial specification. An ambiguous drawing, incomplete quality requirements, or unclear packaging expectations can lead to serious discrepancies.
The supplier manufactures based on the information available to them. If the requirements system is not clear, the result won't be either. In such cases, the quality dispute is often not a breach of contract but a difference in interpretation.
A documented, unambiguous requirements system should be seen not as an administrative burden but as a risk-reduction tool.
Incorrect Incoterms and Liability Structure
An inappropriately chosen Incoterms term is also an internally generated risk. If the company does not precisely understand where risk transfers, or who is responsible for insurance, the handling of problems becomes uncertain.
A common case: the buyer decides based on the lower EXW or FOB price while lacking the infrastructure for logistics control. The subsequent additional costs or loss events are in this case not the supplier's fault but the consequence of the decision.
Understanding the Total Landed Cost and the points of liability must be an in-house professional competency.
Inadequate Supplier Selection Process
Many companies select suppliers based on price alone. The absence of a qualification system, failure to check references, or bypassing an on-site audit can lead to structural problems later.
A supplier's performance is heavily influenced by the standards and measurement structure the buyer applies. Without defined KPIs, quality assessment, or feedback, the relationship remains informal.
This is not a weakness of the supplier – it is a lack of control on the buyer's side.
Currency and Financing Exposure
The currency risk that frequently arises in international procurement is also a consequence of internal decisions. If the company does not consciously manage its currency exposure, an exchange rate movement can immediately lead to deteriorating results.
Similarly, long payment terms or an inadequate security structure can cause liquidity problems. These are also not manufacturing defects but financial decision shortfalls.
What Should the Decision-Maker Ask?
Before blaming the supplier, it is worth clarifying:
- Was the technical specification unambiguous?
- Were the requirements documented?
- Was the appropriate Incoterms term chosen?
- Was there a supplier qualification system?
- Did we account for the Total Landed Cost and currency exposure?
If there is no clear answer to these, the source of the error likely lies to a significant extent in our own internal operations.
Summary
In international procurement, supplier performance is important – but not the sole risk factor. Many import risks stem from the company's own decision-making and operational systems. The real competitive advantage lies not in assigning blame, but in building internal controls and structured operations.
Key Questions
What counts as an internally generated procurement risk? An error or additional cost that stems from imprecise specifications, poor contractual terms, or insufficient controls.
When is the supplier not responsible for a quality deviation? When the requirements were not clearly recorded or documented.
How can internal risks be reduced? Through structured supplier qualification, precise contractual terms, and Total Landed Cost-based decision-making.